A scheduled network infrastructure improvement will be carried out on the storage infrastructure across multiple datacenters according to the following schedule:
13 July – EDC-VE
14 July – EDC-GE
15 July – EDC-FI
20 July – EDC-MI
21 July – EDC-TO
The activity will be performed in phases to improve the resilience and reliability of the underlying storage network infrastructure.
Expected Impact
The maintenance is expected to be transparent for the vast majority of customers.
Any service impact will be limited to a brief interruption of a few minutes during the final phase of the scheduled activities. This interruption is only expected during one of the planned implementation dates. No service interruption is expected during the remaining activities.